New in RayCAD: Connect Conduits, plus AEC Harness, coming soon.See the tools

How Long Does MEPF Tagging Take in Revit?

How to time MEPF tagging in Revit on your own set, how to multiply one sheet into a full project, and what RayCAD's sample sheet run times show.

Written by
Mohit Panchal
Mohit Panchal
Co-founder, RayCAD
Published
Reviewed by
Vipul Panchal
Vipul Panchal
Director, Orbit Engineering Services
Soumyajit Das
Soumyajit Das
Director, Bimtrack Engineering Pvt Ltd
On this page
  1. Time one view in your own project
  2. Multiply the time across the set
  3. What tagging by hand adds up to
  4. Where the time goes
  5. How RayCAD changes the time
  6. Try RayCAD on your own set
  7. Questions
  8. Sources

An MEPF set takes time for three reasons: the number of views, the tags each view needs, and the cleanup after the first pass. Native Revit repeats the same steps on every view. The total therefore grows with the number of views in the set.

Time one view in your own project

Pick one typical floor plan from your current set, then one section. Time each step with a stopwatch or a timer app. Write the results in a table so you can compare views.

  1. Open the view and check that the tag families you need are loaded.
  2. Run Tag All Not Tagged with the right categories and leader settings.
  3. Clean up overlapping tags and adjust leaders by hand.
  4. Check each tag for missing values, such as a tag that shows a question mark.
  5. Note whether the view needs another pass after the latest model change.

Time each step separately. The table shows which step takes the most time on your set.

Here is how the steps usually break down on a commercial office HVAC plan of about 2,600 tags, and on a section view of about 15 tags.

StepOffice floor planSection view
1. Open the view and check tag families10 min30 sec
2. Run Tag All Not Tagged5 min10 sec
3. Clean up overlaps and adjust leaders9.5 h3 min
4. Check each tag for missing values3 h1 min
5. Recheck after the latest model change1.25 h20 sec
Totalabout 14 habout 5 min

Cleanup is most of the time. Tag All places the tags in minutes, then the drafter spends hours moving them clear of each other and routing leaders. For more view types, from residential to hospital plans, see MEPF tagging time across 50 typical views.

Multiply the time across the set

Use this formula to estimate the total:

Total time = time per view × number of views × number of revision rounds

For example, a set with 40 views and three revision rounds repeats the same steps 120 times if every round touches every view. Views that do not change between rounds need less work, so use your own change log to adjust the count.

What tagging by hand adds up to

By hand, tagging runs at about 200 tags an hour on an HVAC plan, and slower on piping, where most tags need a leader. A view of 800 tags takes about 4 hours. A set of 80 such sheets takes about 320 hours, before any revision round.

The capacity calculator starts from those figures. Enter your own sheet count, tag count and rate to see the total for your set.

Where the time goes

On a typical plan, cleanup and checking take more than 90% of the time. On most sets, the check and cleanup steps repeat on every view, so they add up across the project.

How RayCAD changes the time

RayCAD's Auto-Tag runs on the floor plan or section view you select. The sample sheets on this site show the run times below.

  • HVAC sample 01: 1,012 tags in 13 seconds
  • HVAC sample 02: 819 tags in 42 seconds
  • Piping sample 01: 434 tags in 35 seconds
  • Piping sample 02: 434 tags in 36 seconds

These figures cover the run only. A quick glance over the result is still required. RayCAD's Review Tags panel lists the tags that need a second look, with the reason for each. Selecting an item takes you to the element in the view.

Anything RayCAD cannot place cleanly goes to that panel. You do not need to search the sheet for exceptions, and most tags stay out of the panel because they are placed correctly on the first run. Only the tags in the panel need a second look. You also do not need to search for tags that show a question mark.

RayCAD also saves tag families and placement rules as a preset. You set the preset once, then reuse it on every project. Every tag follows the same rules, so the check pass starts from consistent tags. RayCAD runs on your machine, and your model data does not leave it. It works with Revit 2021 to 2027.

Try RayCAD on your own set

Run the 15-day free trial on one of your sheets, then time it against your own table. Use the same view and the same steps so the two numbers compare fairly. To see what the hours mean for a full set, enter your sheet count and tag count in the capacity calculator.

See intelligent tag placement and how RayCAD increases team capacity.

Try RayCAD free for 15 days

What building a per-view tagging timing log yourself really costs

  • Time. Whoever builds and maintains the script is doing software development instead of the billable engineering and drafting work they were hired for.
  • The AI loop.With Claude or ChatGPT it becomes an endless loop of “fix this”, “now fix that”. Each fix can break a case that worked before, and nobody on the team owns the code.
  • Cost. Hours spent building and maintaining scripts, times your hourly rate, against $200 per month for RayCAD for the whole company.

You can build a per-view tagging timing log, and this page shows how. For production MEPF sheets, RayCAD is the cheaper and safer choice. Try it free for 15 days.

Frequently asked questions

How long does Tag All take in Revit?

Revit runs Tag All Not Tagged on one view at a time, so the run is per view. The total depends on how many views you tag and how much cleanup each one needs. Time a typical view in your own project to get a figure you can use.

How long does RayCAD take on a sheet?

On the sample sheets on this site, RayCAD's tagging run took 13 to 42 seconds per sheet. Those figures cover the run only. A quick glance over the result is still required, and any fixes come after it.

Does the time grow with the number of sheets?

Yes. The native steps repeat on every view, so the total grows with the number of views. RayCAD also runs once for each view you select, so the total grows in the same way.

Sources

  1. Autodesk Help, Tag All Not Tagged (Revit 2026) (checked October 21, 2026)
  2. Autodesk Help, Tag All Not Tagged (Revit 2027) (checked October 21, 2026)